Close Menu
News Today | First with the news
  • HOME
  • TAMIL NADU
  • CHENNAI
  • NATION
  • WORLD
  • BUSINESS
  • SPORTS
  • ENTERTAINMENT
  • EDIT
  • COLUMNS
    • POINTBLANK
    • WHY TN IS FORBIDDEN LAND
  • MIXED BAG
    • CLIMATE & WEATHER
    • EDUCATION
    • HEALTH
    • JOBS
    • LEGAL
    • LIFESTYLE
    • SCIENCE
    • TECHNOLOGY
  • E-PAPER
Facebook X (Twitter) Instagram Threads YouTube
  • About us
  • Contact Us
  • Privacy Policy
  • Terms and Conditions
Wednesday, November 25, 2026
Facebook X (Twitter) Instagram
News Today | First with the newsNews Today | First with the news
Login / Register Subscribe
  • HOME
  • E-PAPER
  • TAMIL NADU
  • CHENNAI
  • NATION
  • WORLD
  • BUSINESS
  • SPORTS
  • ENTERTAINMENT
  • EDIT
  • COLUMNS
    • POINTBLANK
    • WHY TN IS FORBIDDEN LAND
  • MIXED BAG
    • CLIMATE & WEATHER
    • EDUCATION
    • HEALTH
    • JOBS
    • LEGAL
    • LIFESTYLE
    • SCIENCE
    • TECHNOLOGY
News Today | First with the news
  • E-PAPER
  • POINTBLANK
  • PRIME PULSE
  • TN ECHOES
  • Asian Games 2026
  • DEEP DIVE
  • GLOCAL
  • COLD FACTS
  • LEADING LIGHTS
  • CRYSTAL GAZING
  • PATTERNS
Home » 470 infra projects show cost overrun of Rs 4.37 lakh cr

470 infra projects show cost overrun of Rs 4.37 lakh cr

AgencyBy AgencySeptember 27, 2021No Comments
🌐 Translate ▾
  • Tamil
  • Hindi
  • Malayalam
  • Kannada
  • Telugu
Share WhatsApp Facebook Twitter LinkedIn Pinterest Telegram Copy Link Email
Mumbai: As many as 470 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.37 lakh crore, according to a report.
The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.
Of the 1,718 such projects, 470 reported cost overruns and 560 were delayed.
”Total original cost of implementation of the 1,718 projects was Rs 21,99,181.52 crore and their anticipated completion cost is likely to be Rs 26,36,710.50 crore, which reflects overall cost overruns of Rs 4,37,528.98 crore (19.90 per cent of original cost),” the ministry’s latest report for August 2021 said.
According to the report, the expenditure incurred on these projects till August 2021 is Rs 12,52,298.40 crore, which is 47.49 per cent of the anticipated cost of the projects.
However, the report said the number of delayed projects decreases to 373 if delay is calculated on the basis of the latest schedule of completion.
Further, for 871 projects neither the year of commissioning nor the tentative gestation period has been reported.
Out of the 560 delayed projects, 96 have overall delay in the range of 1-12 months, 128 have been delayed for 13-24 months, 210 for 25-60 months and 126 projects have delays of 61 months and above.
The average time overrun in these 560 delayed projects is 46.94 months.
Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems are among the other reasons.
The report also cited state-wise lockdowns due to COVID-19 as a reason for the delay in implementation of these projects.
It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are underreported, it added.
Share. WhatsApp Facebook Twitter Telegram Copy Link Email
Previous ArticleIndia needs 4-5 more SBI sized banks: FM
Next Article Fuel supply by Coal India to power sector rises in Aug
Add A Comment

Comments are closed.

Latest Posts

Thiruparankundram: Deepam lit at customary spot, not Deepathoon

NT BureauNovember 24, 20260

In high drama at Thiruparankundram on Tuesday evening, the ceremonial Karthigai Deepam was lit at the customary spot near the Uchipillaiyar temple rather than atop the disputed Deepathoon stone pillar, even after the Madurai Bench of the Madras High Court ordered strict compliance with the Supreme Court’s directive.

NFL clears Steelers’ DK Metcalf of suspension threat

AgencyNovember 24, 20260

Pittsburgh, Nov 24: Pittsburgh Steelers wide receiver DK Metcalf will face no suspension from the…

Notre Dame safety Luke Talich out for season

AgencyNovember 24, 20260

South Bend (Indiana), Nov 24: No. 3-ranked Notre Dame has suffered a major defensive blow…

Arsenal, Manchester City resume Champions League campaign tonight

AgencyNovember 24, 20260

London, Nov 24: Matchday 5 of the 2026–27 UEFA Champions League kicks off on Tuesday…

ICC retains saliva ban despite Shubman Gill appeal

AgencyNovember 24, 20260

New Delhi, Nov 24: The International Cricket Council (ICC) has confirmed it has no plans…

About
About
Facebook X (Twitter) Instagram RSS
Latest Posts
  • Thiruparankundram: Deepam lit at customary spot, not Deepathoon
  • NFL clears Steelers’ DK Metcalf of suspension threat
  • Notre Dame safety Luke Talich out for season
  • Arsenal, Manchester City resume Champions League campaign tonight
  • ICC retains saliva ban despite Shubman Gill appeal
© 2026 NewsTodayNet.com. All Rights Reserved. Designed & Maintained by Gifted Technologies.
  • About us
  • Contact Us
  • Privacy Policy
  • Terms and Conditions

Type above and press Enter to search. Press Esc to cancel.

Ad Blocker Enabled!
Ad Blocker Enabled!
Our website is made possible by displaying online advertisements to our visitors. Please support us by disabling your Ad Blocker.

Sign In or Register

Welcome Back!

Login to your account below.

Prove your humanity: 8   +   10   =  
Lost password?