Close Menu
News Today | First with the news
  • HOME
  • TAMIL NADU
  • CHENNAI
  • NATION
  • WORLD
  • BUSINESS
  • SPORTS
  • ENTERTAINMENT
  • EDIT
  • COLUMNS
    • POINTBLANK
    • WHY TN IS FORBIDDEN LAND
  • MIXED BAG
    • CLIMATE & WEATHER
    • EDUCATION
    • HEALTH
    • JOBS
    • LEGAL
    • LIFESTYLE
    • SCIENCE
    • TECHNOLOGY
  • E-PAPER
Facebook X (Twitter) Instagram Threads YouTube
  • About us
  • Contact Us
  • Privacy Policy
  • Terms and Conditions
Tuesday, November 24, 2026
Facebook X (Twitter) Instagram
News Today | First with the newsNews Today | First with the news
Login / Register Subscribe
  • HOME
  • E-PAPER
  • TAMIL NADU
  • CHENNAI
  • NATION
  • WORLD
  • BUSINESS
  • SPORTS
  • ENTERTAINMENT
  • EDIT
  • COLUMNS
    • POINTBLANK
    • WHY TN IS FORBIDDEN LAND
  • MIXED BAG
    • CLIMATE & WEATHER
    • EDUCATION
    • HEALTH
    • JOBS
    • LEGAL
    • LIFESTYLE
    • SCIENCE
    • TECHNOLOGY
News Today | First with the news
  • E-PAPER
  • POINTBLANK
  • PRIME PULSE
  • TN ECHOES
  • Asian Games 2026
  • DEEP DIVE
  • GLOCAL
  • COLD FACTS
  • LEADING LIGHTS
  • CRYSTAL GAZING
  • PATTERNS
Home Ā» 483 infra projects show cost overruns of Rs 4.43 lakh crore

483 infra projects show cost overruns of Rs 4.43 lakh crore

NT BureauBy NT BureauAugust 23, 2021No Comments
🌐 Translate ā–¾
  • Tamil
  • Hindi
  • Malayalam
  • Kannada
  • Telugu
Share WhatsApp Facebook Twitter LinkedIn Pinterest Telegram Copy Link Email

Mumbai: As many as 483 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.43 lakh crore, according to a report.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of the 1,781 such projects, 483 reported cost overruns and 504 were delayed.

“Total original cost of implementation of the 1781 projects was Rs 22,82,160.40 crore and their anticipated completion cost is likely to be Rs 27,25,408.00 crore, which reflects overall cost overruns of Rs 4,43,247.60 crore (19.42% of original cost),” the Ministry’s latest report for July 2021 said.

According to the report, the expenditure incurred on these projects till July 2021 was Rs 13,22,515.87 crore, or 48.53 per cent of their anticipated cost.

However, the report said the number of delayed projects decreases to 369 if delay is calculated on the basis of the latest schedule of completion.

Further, for 1,001 projects neither the year of commissioning nor the tentative gestation period has been reported.

Out of the 504 delayed projects, 92 have overall delay in the range of 1-12 months, 118 have been delayed for 13-24 months, 178 for 25-60 months and 116 projects have delays of 61 months and above.

The average time overrun in these 504 delayed projects is 46.85 months. Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems are among the other reasons.

The report also cited state-wise lockdowns due to Covid-19 as a reason for the delay in implementation of these projects.

It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are underreported, it added.

 

Share. WhatsApp Facebook Twitter Telegram Copy Link Email
Previous ArticleIndian startups raised $6.5 bn funding in Q2 2021
Next Article Afghan: India brings back 146 of its evacuated nationals
Add A Comment

Comments are closed.

Latest Posts

Convenience not at the cost of privacy

NT BureauNovember 24, 20260

The Union Home Ministry’s warning about the potential misuse of authenticated WhatsApp Web sessions is a timely reminder that digital convenience often comes with security risks. With WhatsApp becoming an integral

Trade talks in Tiruppur

NT BureauNovember 24, 20260

Tiruppur: Vayana TradeXchange (VTX), a cross-border trade finance marketplace, hosted the inaugural chapter of ā€˜Trade Talks’ in Tiruppur, in partnership with the Tiruppur Exporters’ Association (TEA) and with

‘Early health screenings areĀ  good to avoid complications’

NT BureauNovember 24, 20260

‘Twenties and thirties are good time to establish basic health measurements. Blood pressure, weight, waist circumference and family medical history can help identify early risk factors,’ said Dr Shyla Usman Ali, Fertility

Highway Infrastructure advancesĀ  3 major projects worth Rs 630 cr

NT BureauNovember 24, 20260

Highway Infrastructure Limited said it has achieved three significant project execution milestones in a single day, involving projects worth a combined ₹630.17 crore, marking a potentially important phase in the company’s

Trisha Peravai triggers speculations on actress’ political foray

NT BureauNovember 24, 20260

A new organisation named Ilaya Puratchi Thalaivi Trisha Peravai has been established in Tirunelveli, with its founder expressing hopes of seeing actress Trisha become an active participant in Tamil Nadu politics.

About
About
Facebook X (Twitter) Instagram RSS
Latest Posts
  • Convenience not at the cost of privacy
  • Trade talks in Tiruppur
  • ‘Early health screenings areĀ  good to avoid complications’
  • Highway Infrastructure advancesĀ  3 major projects worth Rs 630 cr
  • Trisha Peravai triggers speculations on actress’ political foray
Ā© 2026 NewsTodayNet.com. All Rights Reserved. Designed & Maintained by Gifted Technologies.
  • About us
  • Contact Us
  • Privacy Policy
  • Terms and Conditions

Type above and press Enter to search. Press Esc to cancel.

Ad Blocker Enabled!
Ad Blocker Enabled!
Our website is made possible by displaying online advertisements to our visitors. Please support us by disabling your Ad Blocker.

Sign In or Register

Welcome Back!

Login to your account below.

Prove your humanity: 6   +   7   =  
Lost password?